Home
Hydromix Logo PLANT PRODUCTIVITY
--With--
THE PATENTED HYDROMIX® METHOD OF SLURRY MIXING
& BATCHING
 
BASED ON:   10 YARD LOADS
TYPICAL MIX DESIGN:   (.35 WATER / CEMENT RATIO )

500# CEMENT AND FLYASH
176# WATER (21 GAL.)
3324# AGGREGATE


PRE-LOAD BATCH AND TRUCK POSITIONING TIME:
30 SEC 45 SEC 60 SEC
 
PLUS
HYDROMIX® LOAD TIME:
(CEMENT AND WATER)
 
 
10 SEC YARDS
50# CEM/SEC
332# AGG/SEC
126 GPM
SEC/LOAD
YDS/HR
130 145 160
277 248 225
 
12 SEC YARDS
42# CEM/SEC
277# AGG/SEC
105 GPM
SEC/LOAD
YDS/HR
150 165 180
240 218 200
 
14 SEC YARDS
36# CEM/SEC
237# AGG/SEC
90 GPM
SEC/LOAD
YDS/HR
170 185 200
212 195 180
 
16 SEC YARDS
31# CEM/SEC
208# AGG/SEC
79 GPM
SEC/LOAD
YDS/HR
190 215 220
189 167 164
 
18 SEC YARDS
28# CEM/SEC
185# AGG/SEC
70 GPM
SEC/LOAD
YDS/HR
210 225 240
171 160 150

NOTES:
 
  1. This chart was developed to emphasize the importance of all aspects of plant production: pre-loading the batch, truck positioning, Hydromix® slurry time, and aggregate feed rate.

  2. Hydromix® load time will depend upon correct (recommended) positioning of the unit and the truck hopper acceptance of the aggregate feed rate and water/cement ratio.